The Minnesota Department of Transportation on Thursday released its 2012 construction plan for Minnesota roads. The list includes six projects in or around Burnsville that may have an impact on residents traveling in the area. Many of them concern major routes in and out of town, which could greatly alter your commute to work.
- Hwy. 13
Location:
Description: Resurface road, add turn lanes, improve drainage. In addition, the City of Burnsville will soon embark on a .
Total Cost: $7.9 million
Date: May-Aug 2012
Impact: Lane closures, detours
- Interstate 35E
Location: Hwy. 110
Description: Resurface road, repair concrete and bridge decks
Total Cost: $1.5 million
Date: April-Aug 2012
Impact: Lane and ramp closures
- Interstate 35E
Location: Hwy. 110 east and west ramps
Description: Replace signals
Total Cost: $233,605
Date: Oct-Dec 2012
Impact: Short-term, non-rush hour lane closures
- Interstate 35E
Location: West side of I-35E north of Diffley Rd, Meadowlark Curve to Meadowlark Way in Eagan
Description: Install noise wall and drainage
Total Cost: $511,385
Date: April - July 2012
Impact: Short-term, non-rush hour ramp and shoulder closures
- Hwy. 77
Location: 138th St. in Apple Valley to Minnesota River
Description: Repair concrete, resurface road and upgrade guardrail
Total Cost: $7.5 million
Date: Aug-Nov 2012
Impact: Long-term lane and ramp closures